Notice to Air Carriers serving Spokane International Airport
Proposed Amendment to approved PFC Application #97-03-C-00-GEG
Spokane
Airport Authority received approval from the FAA to "impose
and use" PFCs for eight projects at Spokane International
Airport on March 24, 1997. This #97-03-C-00-GEG was then amended
twice on August 18, 1998 and on January 24, 2003 respectively.
Three of the proposed projects were deleted from the application
through the amendment process previously. All remaining five
projects in this application are now all complete and we have
final actual expenditures. Prior to closing this application
#3, we need to amend the collection and use amounts.
Spokane
Airport Authority is proposing to increase the total amount
of PFC's to be collected on these projects from the current
approved amount of $35,805,772 to $38,175,419. Project #7
Regional Terminal Concourse Extension was approved for $20,566,659.
The project was completed at an actual cost of $21,777,799
due to an increase in the cost of steel, labor and unforeseen
conditions. This resulted in an increase needed of $1,211,140.
Additionally, Project #8 Terminal Ticketing/Baggage Extension
was approved for $12,339,995 previously. The project is now
complete and the actual cost is $13,498,502. This results
in an increase in PFCs needed of $1,158,507. Attached is a
revised PFC project Spreadsheet titled "PFC Amendment
Funding Summary Table" with final project costs and funding
sources.
This
proposed change does not result in a revised estimated expiration
date due to the small increase in the revised collection amount
needed of $2,369,647 and the actual PFC revenue collected
during that time. In accordance with Federal Aviation Regulation
49 CFR Part 158.37 Passenger Facility Charges, Spokane Airport
Authority will hold a consultation meeting with air carriers
to discuss in detail the justification for the Amendment on
Tuesday, May 23, 2006 at 1:00 pm local time, regarding this
proposed amendment. The meeting will be held in the Airport
Board Room located in the Administrative Offices on the second
floor of the terminal building at the Airport.
Spokane
International Airport plans to submit a proposal to amend
and close out GEG PFC#3 as described above to the FAA for
review and approval on June 28, 2006. We solicit your certifications
of agreement or disagreement with the proposed change prior
to the submission of the amendment to the FAA. We propose
this amendment and closeout to be effective on August 1, 2006.
If you have any questions prior to our presentation on May
23, 2006 of this proposal, please contact me.