Spokane International Airport
Proposed
Passenger Facility Charge Application #6
Project Descriptions
I.
ALP Update. This PFC
project consists of preparation of an Update to the ALP. The
ALP was last updated in 2002 and the ALP needs to be updated
to reflect future proposed development of the Airport. Development
resulting from updating the ALP will preserve safety, security and capacity
at the Spokane International Airport. The total cost of this
PFC project is $200,000.
This project is anticipated to start in August 2006
and will be complete by February 2007.
II.
Access Control
System-This PFC project consists of the purchase and installation
of an upgraded new
access control system with associated electrical updates.
The total estimated cost is $500,000.
The current Airport access control system was installed
in 1993 with Edicon/Apollo equipment and was expanded to the
current Lenel head-end equipment. Lenel is phasing out support of legacy products including the Apollo
equipment. The end-of-life
is scheduled to occur near the end of 2007.
The upgrade will include installation of wiring and
electronics necessary to upgrade 80 card readers located in
the terminal and at the perimeter vehicle gates. PFC funding
would pay for 100% of the project costs.
The project start date is April 2007 and will end in
December 2007.
III.
SRE Equipment
- This PFC project consists of two replacement runway sweepers.
The total estimated costs for design and construction
is $800,000. PFC funding
would pay for 100% of the project costs. The new sweepers will be replacing two sweepers
that were originally purchased in 1977 and are 29 years old. The old equipment use two-stroke engines and
have exceeded their life expectancy.
The new equipment will be used to maintain the safe
and efficient operation of the airfield during snow removal.
Project start date will be September 2006 and will
be complete by September 2007.
IV.
Planning
and Design for Runway 3 Extension- This PFC project consists of the
planning and design including the required Environmental Assessment
for the extension of Runway 3 and the necessary associated
taxiway extensions. Included in this project are the planning,
design, and coordination of the enabling projects which include
Electric Avenue road relocation and the navigational equipment
relocation required for the Runway Extension. The total estimated cost for this project $3,500,000
to be paid 100% with PFCs. This project started March 2006
and the expected completion is no later than December 2007.
V.
Construction
of Runway 3 Extension ( IMPOSE ONLY PROJECT)- This project
represents construction of the extension to Runway 3, and
the necessary associated taxiway extensions.
Included in this project is construction of the required
enabling projects, specifically the Electric Avenue road relocation
and the navigational equipment relocation, which are both
required for the Runway Extension. Also included in this project is the required land necessary for
this project. It consists
of the purchase of 12 parcels of land totaling approximately
58 acres required for the Runway Extension. The project start
date is planned for January 2008 and will be complete no later
than November 2009.
Total cost of this project including the enabling projects
is $23,000,000 and will be paid 100% with PFC
funding.
IMPOSE ONLY ALTERNATE PROJECTS
VI.
Airport Entrance
Road Realignment- This project includes the design and construction of
the primary access road to and from the airport. The project will include rechannelization of some lanes, an underpass
at the Spotted Road intersection, and a complete overlay of
the existing road. The
project is necessary to improve the safety of the primary
access road. Due to the frequency of traffic accidents on the road the Washington
State Department of Transportation has assisted with a preliminary
study to identify project scope.
Total cost of this project is estimated to be $19,000,000
and will be paid 100% with PFC funding.
The project start date is planned for January 2008
and will be complete no later than June 2009.
VII.
Snow Removal Equipment Building- This project
consists of an additional building for the storage of snow
removal equipment. With
the removal of three buildings in the area of the new general
aviation taxilanes, the airport does not have adequate facilities
to store the existing equipment. The new facility will be adjacent to the current
SRE facility. The
existing cost estimate for the facility is $4,100,000 and
will be paid for 100% with PFC funding.
This project start date is planned for January 2009
and will be completed no later than September 2010.